PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 3

All technical work is completed on the project. Which of the following remains to be done?
  • A Balance constraints
  • B Solution evaluation
  • C Post implementation assessment
  • D Plan risk responses
Reveal correct answer

Correct answer: B

Explanation

Balancing constraints, and planning the risk responses are done earlier in the project. Once the solution has been built it must be evaluated for business value. Post implementation assessment is usually done AFTER the project is closed.