PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 4

The solution has been completed and tested. The project manager has asked you to show it to the business stakeholders before implementation. One of the key stakeholders finds a serious problem. What should you do?
  • A Assess the impact of the problem.
  • B Tell the stakeholder you will develop a workaround for him.
  • C Talk with the development team and ask them to make a change.
  • D Tell the project manager the implementation must be delayed.
Reveal correct answer

Correct answer: A

Explanation

It is possible that a serious problem might affect your implementation schedule. You may need to develop a workaround or request a change. However, before doing any of these, you need to assess the impact in order to determine the best course of action.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need