Certified Scrummaster CSM · Free Practice Question Medium

Question 22

Which of the following are all involved in the Sprint Backlog?

  • A

    The Sprint Goal, the Product Backlog items selected for the Sprint, and the plan for delivering them.

  • B

    The Definition of Done, the Product Backlog items selected for the Sprint, and the plan for delivering them.

  • C

    The Sprint Goal, the Product Backlog items selected for the Sprint, and the Product Goal.

  • D

    The Product Goal, the Product Backlog items selected for the Sprint, and the plan for delivering them.

Reveal correct answer

Correct answer: A

Explanation

The Sprint Goal, the Product Backlog items selected for the Sprint, plus the plan for delivering them are together referred to as the Sprint Backlog.The Scrum Guide, Page 9

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need