Certified Scrummaster CSM · Free Practice Question Easy

Question 23

Who should order the work for a complex problem into a Product Backlog?

  • A

    Scrum Team

  • B

    The Developers

  • C

    Scrum Master

  • D

    Product Owner

Reveal correct answer

Correct answer: D

Explanation

Scrum requires a Scrum Master to foster an environment where A Product Owner orders the work for a complex problem into a Product Backlog, The Scrum Team turns a selection of the work into an Increment of value during a Sprint, The Scrum Team and its stakeholders inspect the results and adjust for the next Sprint and Repeat.The Scrum Guide, Page 3