Who should order the work for a complex problem into a Product Backlog?
-
A
Scrum Team
-
B
The Developers
-
C
Scrum Master
-
D
Product Owner
Reveal correct answer
Correct answer: D
Explanation
Scrum requires a Scrum Master to foster an environment where A Product Owner orders the work for a complex problem into a Product Backlog, The Scrum Team turns a selection of the work into an Increment of value during a Sprint, The Scrum Team and its stakeholders inspect the results and adjust for the next Sprint and Repeat.The Scrum Guide, Page 3