Project Management Professional PMP · Free Practice Question Medium

Question 173

Eugene is the project manager for Atomic Corporation. While reviewing a recent project proposal, he notices that several deliverables pose a potential safety risk to his project team. What should he do next?
  • A Evaluate the risk and plan additional tasks to mitigate it.
  • B Transfer the risk by hiring an outside consultant to perform that work.
  • C Refuse to work on those deliverables.
  • D Ask the project team for volunteers to perform that work.
Reveal correct answer

Correct answer: A

Explanation

Eugene should evaluate the potential safety risk and add additional tasks to ensure the project remains safe for his team. Refusing to work on those deliverables will negatively impact Eugene’s project. Transferring the risk may be a good option, but not before Eugene has evaluated the risk. Asking for volunteers is not a good option as the risk still exists.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need