Question 168
Jeffrey has talked with all the appropriate people to identify the risks in his agile project at Joshua Jellybeans. The people he is engaged with include
- A The development team.
- B All stakeholders, including the development team, product owner, sponsor, and a few customers.
- C The development team and product owner.
- D The development team and managerial stakeholders, including the product owner.
Reveal correct answer
Correct answer: B
Explanation
All stakeholders, including internal resources, stakeholders, sponsors, and customers, should be involved in identifying risks. All stakeholders should be included in risk identification. All stakeholders should be involved in risk identification throughout the project, so the other answers limit the involved stakeholders.Discussion