Project Management Professional PMP · Free Practice Question Easy

Question 140

Stakeholder identification is essential to effective project managers. All the following are key stakeholders on every project except for which one?
  • A The project management team
  • B Influencers
  • C The project manager
  • D Government agencies
Reveal correct answer

Correct answer: D

Explanation

Government agencies are not critical stakeholders on every project. The project manager is a key stakeholder in every project. The project management team is a vital stakeholder in every project. Influencers are key stakeholders in every project.