Project Management Professional PMP · Free Practice Question Easy

Question 135

As the project manager for Hart Logistics, management has asked for Avi's help in choosing which projects should be implemented. Of the following, which is the most important factor in a project selection model?
  • A Constraint type
  • B Schedule
  • C Business needs
  • D Budget
Reveal correct answer

Correct answer: C

Explanation

Business needs come first in a project selection model. Project constraints are usually not an issue in project selection, but a project's capability to perform within the constraints might be. The project's budget is a type of constraint. The schedule of a project is a type of constraint.