Project Management Professional PMP · Free Practice Question Easy

Question 132

You are the project manager of the ORG Project. This project is similar to the ACT Project you have completed. What method can you use to speed up organizational planning?
  • A Use the project plan of the ORG Project on the PLY Project.
  • B Use the roles and responsibilities defined in the ACT Project on the PLY Project.
  • C Use the project team of the ACT Project on the PLY Project.
  • D Use the project team structure of the ACT Project on the PLY Project.
Reveal correct answer

Correct answer: B

Explanation

When projects are similar in nature, the project manager can use the roles and responsibilities defined in the historical project to guide the current project. The entire project plan of the ACT Project is not needed. Even the roles and responsibilities matrix of the historical project may not be an exact fit for the current project. Copying the project team structure is not the best choice of all the answers presented. Using the same project team may not be feasible at all.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need