Sarah is the project manager for a mechanical engineering consulting firm. The organization has had several major projects that were completed months behind schedule. To rectify this issue, the organization wants to adopt more agile methodologies. However, before these methods can be implemented into the project, what should Sarah do first?
  • A Assess organizational culture and readiness for the proposed agile shift in culture.
  • B Place current projects on hold and adjust them to the new agile changes.
  • C Provide agile training for employees who are willing to participate in the first project team.
  • D Ask workers to vote on whether they want to participate in the new projects.
Reveal correct answer

Correct answer: A

Explanation

Sarah should determine whether the organization is ready for the agile shift in culture. Agile operates significantly differently from predictive projects. She will need to be prepared to coach and mentor the team, field questions, and manage frustrations from stakeholders as they attempt the agile approach in their projects. The other three options are viable solutions but should only be conducted after assessing the organizational culture.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need