Project Management Professional PMP · Free Practice Question Medium

Question 127

Jeffrey is the project manager of the OPO Project for his organization and a portion of his project will be contracted with a vendor. Kelly, the project sponsor of the OPO Project, tells Jeffrey to utilize a screening system for the vendors to help sort out unqualified vendors. Which one of the following is the best example of a screening system?
  • A Vendors must be licensed and bonded in the US state where the work will take place
  • B Bids must be under $250,000
  • C Bids must accompany a detailed proposal with timeline
  • D Vendors must attend the bidders’ conference
Reveal correct answer

Correct answer: A

Explanation

Of all the choices the requirement of vendors to be licensed and bonded in a specific US state is the best example of a screening system. While the other answers could be a screening system, they are not as restrictive as the bonded and licensing requirement.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need