Project Management Professional PMP · Free Practice Question Easy

Question 114

Jessica is the project manager for a project which has just officially begun and is scheduled to last fifteen weeks. The project has a budget of $100,000. Jessica would like to start planning a project schedule but is unsure if she has everything she needs. What is the project document displayed below, and does it help Jessica?


  • A It is a milestone list, and it will let her build the schedule.
  • B It is a list of activities and will help her build the schedule.
  • C It is a list of project team members and will help her build a schedule.
  • D It is a stakeholder register and will not help her with the schedule.
Reveal correct answer

Correct answer: B

Explanation

This is a list of activities, which will help Jessica begin planning a schedule. Without knowing what activities are needed, Jessica will be unable to acquire the right team. A milestone list would be an output of designing a schedule. A stakeholder register is used to track a project's stakeholders. The document displayed is not a list of project team members.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need