Project Management Professional PMP · Free Practice Question Easy
Question 99
Lili is the project manager for Project T, which is midway through its planning stage. Project T is expected to take twenty weeks and has a budget of $1,000,000. While planning tasks for Project T, what should Lili keep in mind to maximize its benefit?
- A The number of stakeholders in the project
- B Identify how each task benefits the project
- C The budget of each task
- D The size of the project team
Reveal correct answer
Correct answer: B
Explanation
By identifying how each specific task benefits the greater project, Lili will be able to maximize Project T's overall benefit. The project team's size, number of stakeholders, and task budgets are essential but do not help Lili maximize Project T’s benefits.Discussion