Project Management Professional PMP · Free Practice Question Easy
Question 83
Bianca is the project manager for the Waterford Company and is currently working her way through procurement management processes. Who should Bianca give the procurement document package to when she has it completed?
- A The client
- B The accounting/finance department
- C The project sponsor
- D Each seller who participates in the bidding
Reveal correct answer
Correct answer: D
Explanation
The procurement document package must be received by every vendor that participates in the bidding. The project sponsor does not need to receive the procurement document package; therefore, this response is incorrect. This response is incorrect because the client does not need the procurement document package. The accounting/finance department does not need a copy of the procurement document package; this response is incorrect.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.