Project Management Professional PMP · Free Practice Question Medium
Question 68
Jerwin is the scrum master for Project V at the World Corporation. Project V operates in several countries worldwide and is intended to deploy a new website for World Corporation. Recently World Corporation announced it was closing an office supporting Project V and is either terminating or moving those workers. What is the next best step for Jerwin?
- A Remove items from the backlog to reduce Project V's scope.
- B Hire additional workers in unimpacted countries.
- C Evaluate the backlog for impacts to Project V.
- D Ask the steering committee to retain as many Project V workers as possible.
Reveal correct answer
Correct answer: C
Explanation
Before acting, Jerwin should determine what impact this will have on the backlog. By reviewing the product backlog, Jerwin can understand what items have been completed, what is left in the queue, and what value has not been delivered to the organization through the project. Hiring additional workers may not be necessary. Asking the steering committee to retain workers may not be necessary. Jerwin would not remove items from the product backlog to reduce scope as this is the product owner's responsibility.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.