Project Management Professional PMP · Free Practice Question Medium

Question 61

Paul's team at General Products uses the Lean Product Development methodology. To increase the value, they get from his work; the team continuously focuses on minimizing
  • A The value provided to the customer.
  • B Waste like late decision-making regarding the work.
  • C Extra features that go beyond the basics required, delays, and incomplete work.
  • D Refactoring of the product.
Reveal correct answer

Correct answer: C

Explanation

Eliminating waste involves the minimization of extra features. Late decision-making is encouraged in this methodology, customer value is maximized, and refactoring is encouraged.