Project Management Professional PMP · Free Practice Question Easy
Question 32
You are a project manager for your organization and your project currently has 29 stakeholders. You’ve been informed, however, that due to a change in the project scope your project will have an additional 13 stakeholders next week. How many more communication channels will be created as a result of the 13 additional stakeholders?
- A $406
- B $78
- C $861
- D 455
Reveal correct answer
Correct answer: D
Explanation
To find the answer to this question you’ll use the formula of N(n-1)/2 where N represents the number of stakeholders. You’ll first find the current number of stakeholder communication channels, based on 29 stakeholders, which is 406. Then you’ll find the number of communication channels with the additional 13 people, which is 861. Finally, you’ll find the difference of 861 and 406 which is 455.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
