Project Management Professional PMP · Free Practice Question Easy

Question 27

You are a project manager for the UYT Project, and you’re working with the project team to build out the project network diagram. You and the team are reviewing the relationships between several activities in the project, and you’re concerned about some of the soft logic the team has used for the activity relationships. Who determines the soft logic about activity relationships in a project?
  • A Project team
  • B Project lead
  • C Project manager
  • D Project sponsor
Reveal correct answer

Correct answer: A

Explanation

Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast-tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need