Project Management Professional PMP · Free Practice Question Medium
Question 18
Ike is the project manager for Project Flint, which is in its sixth week of a twelve-week implementation, has a CPI of 1.06 and an SPI of 1. The stakeholders are happy with the project performance but would be thrilled to have the project done as quickly as possible. While reviewing upcoming tasks, Ike noticed that several tasks could easily be completed early and immediately deliver value. What should Ike do with this information?
- A Escalate the decision to the steering committee.
- B Assign a team member to investigate further.
- C Confirm there is no negative impact, then complete the tasks early.
- D Do nothing. Ike should follow the project schedule.
Reveal correct answer
Correct answer: C
Explanation
If Ike can complete the tasks without negatively impacting Project Flint, he should. This will ensure the corporation can benefit from the value they provide. Doing nothing is not optimal as Ike has the chance to deliver value earlier than expected. The steering committee is likely not the best option as they will require further information. Assigning a team member to investigate is not ideal as Ike is responsible for scheduling the project work.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.