Question 17

The management team at Aqua Blue Pools has asked Rosa, their project manager, to define the correlation between the project scope and quality. Of the following, which is the best answer for Rosa to give?
  • A Quality is the process of scope completion to meet stated or implied needs.
  • B Quality evaluates the project scope to make sure quality exists.
  • C The project scope includes quality metrics.
  • D Quality metrics are applied to the project scope.
Reveal correct answer

Correct answer: A

Explanation

In regard to project scope, quality is about finishing the work as promised and is defined in the project scope. Part of what the customer expects is part of the project deliverables. Although the project scope has acceptance requirements, it might not define metrics for quality; this answer is incorrect. This answer is incorrect because it defines quality control. Rosa and her project team will inspect the work results to create the project scope to ensure quality exists within the project. This answer is incorrect because although the project scope has acceptance requirements, metrics for quality may not be defined.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need