Professional Scrum Master I PSM I · Free Practice Question Easy
Question 102
Which statement is true about the duration of a Sprint?
(choose the best answer)
- A The duration of a Sprint is determined during Sprint Planning and should be long enough to complete all planned work items
- B The duration of a Sprint must be one month or less
- C The duration of a Sprint should be adjusted based on the amount of work completed in previous Sprints
- D The duration of a Sprint is determined during Sprint Planning and should include time for development and testing
Reveal correct answer
Correct answer: B
Explanation
According to the Scrum Guide, the heart of Scrum is a Sprint, which is a time-box of one month or less during which a "Done," usable, and potentially releasable product Increment is created. Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint.Discussion