Professional Scrum Master I PSM I · Free Practice Question Medium
Question 97
When should the Product Owner participate in the Daily Scrum?
(select the best answer)
- A Whenever the Developers need clarification regarding Product Backlog items.
- B Whenever the Product Owner is working on items on the Sprint Backlog: however, they participate as a Developer.
- C Whenever the Product Owner has updates regarding the marketplace.
- D Whenever the Scrum Master tells the Product Owner to be there.
Reveal correct answer
Correct answer: B
Explanation
The Product Owner should participate in the Daily Scrum "Whenever the Product Owner is working on items on the Sprint Backlog: however, they participate as a Developer." The Daily Scrum is an event primarily for the Developers to inspect progress towards the Sprint Goal and adapt the Sprint Backlog as necessary. The Product Owner may attend if they are actively contributing to items in the Sprint Backlog, but they participate as a Developer in this context.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.