Question 96

Which three statements are correct when four teams are working on a product?

(Select the best three answers)

  • A There can be multiple Scrum Masters.
  • B There can be multiple Definitions of Done.
  • C There can be multiple Product Backlogs.
  • D Each Scrum Team maintains its individual Sprint Backlog.
  • E There is only one Sprint Backlog each Sprint.
  • F There is only one Definition of Done.
Reveal correct answers

Correct answers: A, B, D

Explanation

"There can be multiple Scrum Masters" - If you have four Scrum Teams working on a product you might have one Scrum Master per Scrum Team, for instance; which implies that you might have multiple Scrum Masters. "There can be multiple Definitions of Done". "There is only one Definition of Done". - The product must have one Definition of Done. However, each Scrum Team might have its own Definition of Done containing stringent criteria, compared to the product's Definition of Done. The combination of the work of all Scrum Teams must adhere to the product's Definition of Done. "There can be multiple Product Backlogs". - A Single Product Backlog exists for a Product. "Each Scrum Team maintains its individual Sprint Backlog". "There is only one Sprint Backlog each Sprint". - Each Scrum Team has its own Sprint Backlog.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need