Professional Scrum Master I PSM I · Free Practice Question Medium
Question 77
True or False: The Definition of Done is created during the first Sprint and remains unchanged until the end of the project.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
During the Sprint Retrospective, the Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. Thus, the Definition of Done can be adapted.Discussion