Question 61

True or false: Product Owner can delegate the responsibility of sizing the Product Backlog to the Scrum Master.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, the Developers who will be doing the work are responsible for the sizing. The Product Owner may influence the Developers by helping them understand and select trade-offs.