Professional Scrum Master I PSM I · Free Practice Question Easy
Question 62
Who is accountable for explaining the Product Backlog items?
(choose the best option)
- A The Developers are self-managed and have to talk to anyone necessary and find out the meanings of items.
- B The Business Analyst
- C The Product Owner
- D The Scrum Master
- E The user's representative
Reveal correct answer
Correct answer: C
Explanation
The Product Owner is accountable for ensuring that the Product Backlog is transparent, visible, and understood.Discussion