Question 57
Which of the following has the most to do with capturing and using lessons learned?
(Select the best answer)
- A Sprint Planning
- B Product Backlog Refinement
- C Sprint Retrospective
- D Sprint Review
Reveal correct answer
Correct answer: C
Explanation
Sprint Retrospective is about discussing the way work was done and finding ways to improve it next time; this is mainly about lessons learned.Discussion