Professional Scrum Master I PSM I · Free Practice Question Easy
Question 58
Who is primarily responsible for coaching the Scrum Team and ensuring Scrum is used correctly?
(choose the best answer)
- A Product Owner
- B Scrum Master
- C Developers
- D Stakeholders
Reveal correct answer
Correct answer: B
Explanation
According to the Scrum Guide, the Scrum Master is responsible for ensuring Scrum is understood and implemented correctly. They facilitate the Scrum events, coach the Scrum Team, and help remove any obstacles that hinder progress.Discussion