Question 25

True or False: The duration of a Sprint can exceed one month for large products.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

According to the Scrum Guide, a Sprint is time-boxed to a maximum duration of one month or less. This time-boxed nature provides a consistent rhythm and ensures that the team can inspect and adapt frequently. Therefore, the statement that the maximum duration of a Sprint may be more than one month for large products is false.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.