Professional Scrum Master I PSM I · Free Practice Question Easy
Question 25
True or False: The duration of a Sprint can exceed one month for large products.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
According to the Scrum Guide, a Sprint is time-boxed to a maximum duration of one month or less. This time-boxed nature provides a consistent rhythm and ensures that the team can inspect and adapt frequently. Therefore, the statement that the maximum duration of a Sprint may be more than one month for large products is false.Discussion