Professional Scrum Master I PSM I · Free Practice Question Hard

Question 26

True or False: If the Developers realize they have selected too much work to finish in the Sprint, they should reduce the Definition of Done and get all of the Product Backlog items done by the new definition.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

If the Developers realize they have taken on too much work for a Sprint, reducing the Definition of Done is not the appropriate response. The Definition of Done is a set of shared understandings about what it means for work to be complete. It should be a standard that ensures quality and is not something that should be changed to accommodate an overbooked Sprint. Instead, the Developers should work with the Product Owner to negotiate which items in the Sprint Backlog can be removed or postponed, ensuring that the most valuable work remains. It is key that the Scrum Team communicates openly and regularly about progress to make these adjustments as necessary.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need