Question 18

During a Sprint, what activities might a Product Owner engage in?

(choose the best answer)

  • A Respond to questions from Developers about items in the current Sprint
  • B Facilitate the Daily Scrum
  • C Assign tasks to Developers from the Sprint Backlog
  • D Report to management on the progress of the Sprint
Reveal correct answer

Correct answer: A

Explanation

According to the Scrum Guide, the Product Owner is responsible for maximizing the value of the product resulting from the work of the Scrum Team. During a Sprint, the Product Owner may engage in activities such as answering questions from the Developers about items in the current Sprint to help clarify requirements and ensure that the work being done is aligned with the Product Goal.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need