Question 17
True or False: Sprint Review is not a formal meeting.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
Scrum prescribes four formal events for inspection and adaptation: Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. Be alert: the word formal is used in two distinct ways! First, the four formal events for inspection and adaptation, which means a formal opportunity. A formal meeting means a meeting where people approve something and exchange signatures. In that sense, none of the events are formal meetings. The Sprint Review meeting is informal, not a status meeting, and the Increment presentation is intended to elicit feedback and foster collaboration.Discussion