Question 16
Who is responsible for setting and maintaining the Definition of Done?
(choose the best answer)
- A The Product Owner
- B The Scrum Master
- C The Scrum Team
- D The Stakeholders
- E The Developers
Reveal correct answer
Correct answer: C
Explanation
The Scrum Team, which includes the Product Owner, Scrum Master, and Developers, is collectively responsible for setting and maintaining the Definition of Done. It is a collaborative effort to define the criteria that must be met for a Product Backlog item to be considered complete. The Scrum Team ensures that the Definition of Done is adhered to throughout the development process to maintain a consistent standard of quality for the product increment.Discussion