Professional Scrum Master I PSM I · Free Practice Question Easy
Question 12
Who is responsible for starting the Daily Scrum?
(choose the best answer)
- A The Scrum Master, to make sure the event happens and stays within the timebox.
- B The person who arrives last to encourage punctuality and keep the event within the timebox.
- C Whoever the Developers choose to start.
- D The person holding the talking stick.
Reveal correct answer
Correct answer: C
Explanation
The Daily Scrum is started by whoever the Developers decide should start. The Daily Scrum is an event for the Developers, and they are responsible for conducting it. The Scrum Master's role is to ensure that the event takes place and stays within the timebox, but it is up to the Developers to decide how to conduct the event.Discussion