Professional Scrum Master I PSM I · Free Practice Question Medium
Question 7
You are the Scrum Master of a Scrum Team that is about to start working. One of the things that you need to define the Sprints' length. Which of the following is a factor that should be considered for this purpose?
(choose the best answer)
- A The release schedule of the organization
- B The same length as all the other Scrum Teams in the organization
- C The availability of the Scrum Team members
- D The need for feedback to learn based on doing work and measuring results
Reveal correct answer
Correct answer: D
Explanation
In Scrum, risk is minimized by having at most one month Sprints. The larger the uncertainty, the more the Scrum Team needs feedback on shorter cycles; hence, shorter Sprints. Another factor that might be useful is synchronizing the development cycle with other business events.Discussion