True or False: Is it accurate to say that the Sprint Backlog is created during Sprint Planning and includes the Sprint Goal?
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
According to the Scrum Guide, the Sprint Backlog is composed of the Sprint Goal, the set of Product Backlog items selected for the Sprint, and a plan for delivering the Increment and realizing the Sprint Goal. The Sprint Backlog is created during Sprint Planning, where the Scrum Team collaborates to define a Sprint Goal and select Product Backlog items that will help achieve that goal.Discussion