Prince2 7 Foundation · Free Practice Question Easy

Question 33

What is an advantage of applying the manage by exception principle?
  • A It allows the project team to delegate the authority for day-to-day control of a project to the project manager
  • B It allows the project board to delegate cost tolerances to the project manager
  • C It allows the project team to fully understand their roles and responsibilities
  • D It allows the project team to identify improvements to be made during the project
Reveal correct answer

Correct answer: B

Explanation

OBJ 2.1: A PRINCE2 project has defined tolerances for each project objective to establish limits of delegated authority. This is an advantage of applying the manage by exception principle.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need