Prince2 7 Foundation · Free Practice Question Easy
Question 31
Which statement about the project manager role is CORRECT?
- A It is responsible for the day-to-day management of a project
- B It is an optional role for a PRINCE2 project
- C It is a single point of accountability for the project
- D It can be combined with the project assurance role
Reveal correct answer
Correct answer: A
Explanation
OBJ 3.2.3: The project manager is the single focus for theday-to-day management of a project. This person has the authority to run the project on behalf of the project board within the constraints determined by the project board. The role of the project manager must not be shared.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.