Prince2 7 Foundation · Free Practice Question Easy
Question 30
Which of the following is an objective of the controlling a stage process?
- A Review and, if necessary, update the project initiation documentation
- B Check that all of the project's products have been accepted by the users
- C Ensure that the business case is kept under review
- D Obtain approval for the project plan from corporate, program management, or customer
Reveal correct answer
Correct answer: C
Explanation
OBJ 4.2: The objective of the controlling a stage process is to ensure that the business case is kept under review. The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.Discussion