What is the third step in the recommended risk management procedure?
  • A Assess
  • B Identify
  • C Implement
  • D Plan
Reveal correct answer

Correct answer: D

Explanation

OBJ 3.5.4: The third step is plan. The risk must first be identified before it can be assessed, and responses planned and then implemented.