Prince2 7 Foundation · Free Practice Question Easy
Question 29
What is the third step in the recommended risk management procedure?
- A Assess
- B Identify
- C Implement
- D Plan
Reveal correct answer
Correct answer: D
Explanation
OBJ 3.5.4: The third step is plan. The risk must first be identified before it can be assessed, and responses planned and then implemented.Discussion