Prince2 7 Foundation · Free Practice Question Easy
Question 28
Which document should describe how PRINCE2 has been tailored for a particular project?
- A Risk management approach
- B Project plan
- C Communication management approach
- D Project initiation documentation
Reveal correct answer
Correct answer: D
Explanation
OBJ 2.1: The project initiation documentation (PID) should describe how PRINCE2 has been tailored for that particular project so that all those involved in the project understand how PRINCE2 is to be used and how to carry out their particular responsibilities. Tailoring requires the project board and the project manager to make proactive choices and decisions on how PRINCE2 will be applied. When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings). While the risk management approach and communication management approach are a part of the PID, they individually are not where tailoring for a project is documented.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.