Prince2 7 Foundation · Free Practice Question Easy
Question 20
What must be used, as a minimum requirement, for applying the progress theme?
- A Stage authorization
- B Highlight reporting
- C Work package authorization
- D Checkpoint reporting
Reveal correct answer
Correct answer: A
Explanation
OBJ 3.7.2: To meet the requirements of PRINCE2, at a minimum a project must define its approach to controlling progress in the PID, manage by stages, set tolerances, and be managed by exception against them, review the business justification when exceptions are raised, and learn lessons. Manage by stages includes the concept of using stage authorizations from the project board through the directing a project process.Discussion