Prince2 7 Foundation · Free Practice Question Medium

Question 14

Which describes the plan step within the recommended risk management procedure?
  • A Project support allocates the risk budget to fund the selected risk responses
  • B The risk owner decides the best response to control the risk
  • C The risk owner and the risk actionee carry out activities to control and deal with the risk
  • D The project manager formulates the risk management approach
Reveal correct answer

Correct answer: B

Explanation

OBJ 3.5.4: Risk responses are decided by the project team during the plan step. The plan step involves identifying and evaluating the appropriate risk response to remove or mitigate threats, and to maximize opportunities.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need