Prince2 7 Foundation · Free Practice Question Medium
Question 14
Which describes the plan step within the recommended risk management procedure?
- A Project support allocates the risk budget to fund the selected risk responses
- B The risk owner decides the best response to control the risk
- C The risk owner and the risk actionee carry out activities to control and deal with the risk
- D The project manager formulates the risk management approach
Reveal correct answer
Correct answer: B
Explanation
OBJ 3.5.4: Risk responses are decided by the project team during the plan step. The plan step involves identifying and evaluating the appropriate risk response to remove or mitigate threats, and to maximize opportunities.Discussion