Question 13

Which is a benefit of applying the manage by exception principle?
  • A The project management team will understand the tolerances allowed
  • B The project management team will understand the customer's expectations
  • C The project will have review and decision points so that progress can be assessed
  • D The key stakeholders in the project will have representation on the project board
Reveal correct answer

Correct answer: A

Explanation

OBJ 2.1: Understanding delegated authority and established tolerances is a benefit of applying the manage by exception principle. A PRINCE2 project has defined tolerances for each project objective, to establish limits of delegated authority. PRINCE2 enables appropriate governance by defining distinct responsibilities for directing, managing, and delivering the project and clearly defining accountability at each level. This implementation of manage by exception provides for very efficient use of senior management time as it reduces senior managers’ time burden without removing their control by ensuring decisions are made at the right level in the organization.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need