Prince2 7 Foundation · Free Practice Question Easy

Question 5

Which of the following is an objective of the managing product delivery process?
  • A To enable the project board to commit resources and expenditure required for the initiation stage
  • B To review and, if necessary, update the project initiation documentation
  • C Assure the project board that all products in the stage plan for the current management stage have been completed and approved
  • D To ensure a periodic review is carried out to approve the completed products created within the current stage
Reveal correct answer

Correct answer: D

Explanation

OBJ 4.2: Products are assessed and approved when they are completed, during the managing product delivery process. These quality checks are not left until the end of the stage.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.