Prince2 7 Foundation · Free Practice Question Easy

Question 6

Who is responsible for documenting any tailoring of the project plan?
  • A The executive
  • B The project manager
  • C A team manager
  • D Project support
Reveal correct answer

Correct answer: B

Explanation

OBJ 2.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Regardless of the document being considered, any tailoring must be documented by the project manager in the project initiation documentation (PID).

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples