PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 80

The most successful agile projects in the systems thinking approach can be classified as:
  • A Having low technical complexity and low requirement complexity
  • B Having highly uncertain technology and highly uncertain requirements
  • C Having complex technology and complex requirements
  • D Having high requirement complexity and high technical complexity
Reveal correct answer

Correct answer: C

Explanation

The correct answer is having complex technology and complex requirements. Although Agile projects have complex technology and requirements, they do not have technology or requirements that are near chaotic. The other answers are incorrect because they are not accurate depictions of highly successful agile projects. The most successful are neither high nor low, but somewhere in the middle of the complexity standards.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need