PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 49

A Kanban board is a great visual aid to assist in the review of:
  • A The planning of work over the course of a release
  • B The reasons for any bottlenecks in the current iteration
  • C The priority and stage for work items in the current iteration
  • D All items waiting in the backlog that need to be prioritized
Reveal correct answer

Correct answer: C

Explanation

The correct answer is the priority and stage for work items in the current iteration. A Kanban board is a visual representation of the work that needs to be done, what is currently being worked on, and what has been completed. It helps teams see the status of work at a glance and can be used in conjunction with Agile project management software.The other choices are incorrect. A Kanban board does not help the team visualize the backlog or a release, and it does not give the reason for a bottleneck.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need