Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 47

Each of the tools and techniques listed below is used to obtain resources, except for:
  • A The multicriteria decision analysis
  • B The pre-assignment
  • C The staffing management plan
  • D Negotiation techniques
Reveal correct answer

Correct answer: C

Explanation

The staffing management plan is a component of the resources management plan and is not a tool or technique that is used to acquire the project team. Plans are either inputs or outputs; they are never tools or techniques.The tools and techniques used to acquire the project team are pre-assignment, acquisition, negotiation, virtual teams, and multi-criteria decision analysis. PRM9.2.251

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need