Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 47
Each of the tools and techniques listed below is used to obtain resources, except for:
- A The multicriteria decision analysis
- B The pre-assignment
- C The staffing management plan
- D Negotiation techniques
Reveal correct answer
Correct answer: C
Explanation
The staffing management plan is a component of the resources management plan and is not a tool or technique that is used to acquire the project team. Plans are either inputs or outputs; they are never tools or techniques.The tools and techniques used to acquire the project team are pre-assignment, acquisition, negotiation, virtual teams, and multi-criteria decision analysis. PRM9.2.251Discussion