Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 48

You are a project manager for your organization. Your project utilizes a vendor to complete all of the electrical work within your project. Your stakeholder has requested a change in the scope of the project which will cause additional work for the vendor. Which of the following documents will dictate how the change will proceed in regard to the vendor?
  • A The change control documentation
  • B The scope document
  • C The procurement management plan
  • D The contract
Reveal correct answer

Correct answer: D

Explanation

The contractual agreement between the vendor and the customer override all other documents. 1 is incorrect. The change control system should comply with the contractual agreement between the vendor and the customer. 2 is incorrect because the scope details the project work, not the contractual obligations between the vendor and the customer. 3 is also incorrect because the procurement management plan is not as specific as the terms defined within the contract.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need